Second turbine of Vinh Tan 4 thermal power plant starts operation
VGP - The second turbine of the Vinh Tan 4 thermal power plant began generating electricity for the national grid on October 3, nearly three months after the operation of the first one.
The plant has two turbines with a combined capacity of 1,200 MW and was built at a cost of VND36 trillion (US$1.58 billion).
In full operation, it is expected to generate about 7.2 billion kWh each year. It is the first large-scale coal-fueled thermal power plant in Viet Nam using the supercritical steam generator.
The plant is also hoped to contribute to socio-economic development in the South Central Region and raise the stability and economic operation of the national grid.
By Thuy Dung