Refinery back in full operation
VGP - Two months after the first maintenance work was carried out on the Dung Quất Refinery, operations resumed at full capacity from September 14.
September 15, 2011 4:49 PM GMT+7
![]() |
The Dung Quất Refinery |
He said that during the maintenance work, experts fixed 55 technical problems.
Experts also increased the refinery's crude oil capacity by 34%, so that operations can continue uninterrupted when bad weather disrupts the delivery of imported oil.
Operations started at the refinery in February 2009, and to date, it has imported more than 12 million tons of crude oil./.