Under the assignment, the consultant will prepare a comprehensive feasibility study to provide a basis for investment decisions, while completing FEED and bidding documents for subsequent construction packages.
The study will assess key issues, including technology selection, investment structure, financing arrangements and overall project viability. It will also examine opportunities to mobilize non-state funding, including domestic and foreign investment through public-private partnership (PPP) arrangements, subject to financial feasibility and investment recovery prospects.
The consultant is also required to ensure consistency across the railway system and associated infrastructure, provide accurate baseline data, strengthen coordination among relevant stakeholders, and comply with Vietnamese regulations and international standards.
Given the project's unprecedented scale and technical complexity, the TV-02 consulting package is expected to establish a solid technical, technological and organizational foundation for project implementation and the future development of Viet Nam's high-speed railway network.
The package covers surveys, preparation of the feasibility study, front-end engineering design (FEED), and bidding documents, with a proposed contract value of over VND10.24 trillion (US$393 million) and an implementation period of 30 months.
France's SYSTRA will lead the consortium, alongside RoK partners Sambo Engineering Co., Ltd., Yooshin Engineering Corporation and Korea National Railway. Vietnamese members include Transport Engineering Design Inc. (TEDI), TEDI SOUTH, TRICC and HOANG LONG.
The Thang Long Project Management Board and the consortium will proceed with contract negotiations, with the results serving as the basis for signing the official TV-02 contract.
TV-02 is considered the most important consulting package in the investment preparation phase of the mega railway project. Its estimated package price exceeds VND10.78 trillion. The procurement was conducted through direct international appointment under a one-stage, one-envelope procedure.
The contract will apply fixed unit prices to survey activities and a lump-sum arrangement to the feasibility study, FEED and bidding documents, with all deliverables scheduled for completion within 30 months.
In May, the Ministry of Construction organized a roadshow to introduce the feasibility study consulting package to potential bidders and collect market feedback.
The ministry also targets to begin construction of the North-South high-speed railway in December next year.
The North-South high-speed railway has the total length of around 1,541km, starting at Ngoc Hoi station in Ha Noi, running through 15 cities and provinces, and ending at Ho Chi Minh City's Thu Thiem station.
The railway, with a designed speed of 350km per hour, has total investment capital of US$67.34 billion
Once completed, the railway will reduce travel time from Ha Noi capital to Ho Chi Minh City – the country's largest economic engine, to about 5.5 hours./.