Nhon Trach 3 power plant connected to the national grid on February 5 - Photo: tuoitre.vn
The 50MW plant wll be put into commercial operation from July 2025 after testing phase starting February 5.
Located in Phuoc Khanh commune, Nhon Trach district of the southern province of Dong Nai, the Nhon Trach 3 and 4 Power Plants are among Viet Nam's most significant energy projects.
With a total investment of US$1.4 billion, they have a combined capacity of 1,624 MW. When fully operational, they will provide about nine billion kWh of electricity per year to the national grid.