Quang Trach-Pho Noi 500kV circuit-3 power transmission project must be completed prior to September

VGP - Prime Minister Pham Minh Chinh has requested relevant ministries, sectors, agencies, and localities to complete Quang Trach-Pho Noi 500kV circuit-3 power transmission line project prior to September this year.

Posts Kim Loan

August 14, 2024 8:35 PM GMT+7
Quang Trach-Pho Noi 500kV circuit-3 power transmission project must be completed prior to September- Ảnh 1.

Prime Minister Pham Minh Chinh (center) addresses a meeting to review progress of the Quang Trach-Pho Noi 500kV circuit-3 power transmission line project, Ha Noi, August 13, 2024 - Photo: VGP/Nhat Bac

The Government chief made the request at a meeting to review the implementation of the project in Ha Noi on August 13.

The Prime Minister demanded authorities and contractors to mobilize human resources and equipment to speed up the construction progress to finalize the project on schedule.

The transmission line, running from the central province of Quang Binh to the northern province of Hung Yen, has a total length of about 519 km and an investment of VND22 trillion (US$875.62 million), with four component projects crossing nine provinces. I

Construction of the transmission line began in January 2024.

The project is expected to help increase power transmission capacity from the central region to the North from 2,200 MW to 5,000 MW, something which is critical to solving power shortages in the northern region during peak summer months.

It also plays an important role in ensuring the country’s energy security and requires the engagement of ministries, departments and authorities of all localities through which it runs./.